Library Construction Reimbursement Regulations

Regulations for public library construction/renovation reimbursement funding under 29-6-6 of the Rhode Island General Laws. Print Version

Contents

  1. Projects initiated prior to the reinstatement of the construction reimbursement program
  2. General Requirements
  3. Project Requirements
  4. Construction Grant Program Reimbursement Funding and Priorities
  5. Application Procedures
  6. Allowable Costs
  7. Contractor Requirements
  8. Amendments
  9. Display of Signs
  10. Completion of Project

1.  Projects initiated prior to the reinstatement of the construction reimbursement program

Any public library that completed or completes a construction project between July 1, 1992 and July 1, 2000 which was initiated prior to the implementation of the rules and regulations promulgated to implement Governor Lincoln Almond's Executive Order 98-4 (Appendix E [pdf] ), which reinstates the program of state aid for public library construction and capital improvements as specified in Rhode Island General Laws, Section 29-6-6 (Appendix D), is eligible to apply for construction reimbursement funding through the Office of Library and Information Services. Only costs financed by bonds, mortgages or other loan instruments would be eligible for reimbursement. Reimbursement payments for projects approved for funding under this program would begin in state fiscal year 2000, or in the state fiscal year following the completion and acceptance of the completed project by the Office of Library and Information Services.  Such projects are exempted from any of the provisions in these regulations that may not be applicable to a project which has already been completed or is under construction.

Back to Contents


2. General Requirements

These are the general requirements for the construction/renovation of public library facilities for areas where facilities are inadequate for the development of good library services.

2.1. The library must be legally established as a public library according to the General Laws of Rhode Island (Title 29, Chapter 4).

2.2. The library must have a regular source of operating income.

2.3. The library must be eligible for grant-in-aid to cities and towns (Title 29, Chapter 6).

2.4. The library shall furnish proof that the governing body providing operating funds has agreed to provide appropriations so that the new building area can be properly operated, and services to be provided will be properly funded.

2.5. Matching project funds must currently be available at the time an agreement is signed with the library. The library must also provide for the total funds needed to complete the project and cover interest costs until reimbursement of the state share begins in the state fiscal year (July through June) following the completion, audit, and acceptance of the completed project by the Office of Library and Information Services. Reimbursement of the state share will take place over a period of up to twenty years, with one-twentieth of the principal, plus the actual interest cost of borrowing the state share paid each year. Usually a library or the city or town borrows the state share, entering into a mortgage or loan agreement or issuing bonds to cover the period of state reimbursement funding.

2.6. The Office of Library and Information Services must approve both building plans and site.

2.7. The library must present the following information:

2.7.1. What is the adequacy of the present library service in the area?

2.7.2. If the library service is inadequate, in what specific measure will this proposed construction improve the service?

2.7.3. What relationship does this proposed construction have to overall planning for libraries in the area? Is the proposed construction included in the Comprehensive Community Plan? If there is a Library Council, has this proposal been approved by said Council?

2.7.4. How does the library relate its present plan for construction to the future of the community and the future library needs of the area?

Back to Contents


3. Project Requirements

3.1. A professional librarian with experience of library construction projects must serve as consultant to the library director, library board and/or building committee and to the architect throughout the planning and construction of the building.

3.2. There must be a written program prepared by the library director or consultant prior to the designing of the building by the architect.

3.3 The library must have a long range plan covering a period of at least five years.

3.4. The building program must be in keeping with the library's program of service.

3.5. The library must ensure project compliance with all of the assurances required for state funding listed in Appendix C [pdf]. These include, but are not limited to, issues related to handicapped access, EEO Compliance, Minority Business Enterprises and historic preservation. Please read Appendix C very carefully, and make sure your architect gets a copy to include in the construction specifications.

3.6. Projects shall be in compliance with Rhode Island General Law 29-6-6  (Appendix D).

3.7. The library will not dispose of or encumber its title or other interests in the site and facilities during the period of reimbursement of the state share of the project funding.

3.8. Facilities built or remodeled under a construction agreement with the Office of Library and Information Services must continue to be used as free public library facilities unless their use for another purpose is approved by the State of Rhode Island's Chief Information Officer.

3.9. The library will follow such procedures, submit such reports, maintain such records, and afford access thereto, as the Office of Library and Information Services may find necessary.

3.10. At the completion of the project the State of Rhode Island Department of Administration or its designee shall perform an audit in accordance to the funding principles established by the Office of Library and Information Services.

3.11. The library shall retain all financial records until notified by the Office of Library and Information Services that records are no longer needed for program administrative review.

3.12. The library shall provide the Office of Library and Information Services, through an authorized representative, access to and the right to examine all records, books, papers, or documents related to the grant.

Back to Contents


4. Construction Grant Program Reimbursement Funding and Priorities

4.1. Priorities for construction projects are established by the Library Board of Rhode Island on a biennial basis. Current priorities are listed in Appendix F.

4.2. Agreements for construction projects will be entered into on a priority basis, with the estimated amount required for state reimbursement amounts in any given fiscal year to remain below the cap established by the Library Board of Rhode Island (Appendix F).

4.3. Reimbursement for state funds is for up to fifty percent of the total allowable project costs according the Rhode Island General Laws 29-6-6, within parameters established for the rate/share by the Library Board of Rhode Island for maximum per square foot and/or total state share (Appendix F).

Back to Contents


5. Application Procedures

5.1. A copy of the project checklist used by the Office of Library and Information Services is included as Appendix B [pdf].

5.2. As soon as the library begins initial discussions about a construction project, a letter of intent should be sent to the Office of Library and Information Services.

5.3. Based on a summary of the space needs included in the Building Program the library shall submit a preliminary project budget to the Office of Library and Information Services.

5.4. When preliminary estimates and preliminary architectural plans and drawings are completed, the library shall submit a construction project application (Appendix A [pdf]) to the Office of Library and Information Services.

5.5. After a meeting between the Office of Library and Information Services, the library and the architect to review the application and architectural plans, a final assessment will be made by the Office of Library and Information Services.

5.6. The Office of Library and Information Services will participate in the development of the loan or mortgage agreement, assuring the lender of its participation in the project and agreeing to the total amount of capital and interest to be reimbursed and to the terms of the mortgage or other loan(s).      

5.7.  Upon final approval of the project, the Office of Library and Information Services will enter into the agreement with the library. A sample construction agreement has been included as Appendix H .

Back to Contents


6. Allowable Costs include the following:

6.1. Construction of new buildings to be used specifically as public library facilities.

6.2. Expansion, remodeling, and alteration, as distinguished from maintenance and repair, of existing buildings to be used for public library purposes.

6.3. Construction, expansion, remodeling and alteration of the portion of a multipurpose building in which a library is to be housed. Costs relating to those portions of the shared mechanical, meeting room and multipurpose areas which count toward the square footage of the library will be also be eligible.

6.4. Expenses related to

6.4.1. acquiring land on which there is to be new building or expansion of an existing library building

6.4.2. acquiring a building to be converted to a library and expanded, if necessary, if these expenses were incurred within three fiscal years preceding the fiscal year in which the project was approved by the state agency. Such expenses  must constitute actual cost or transfer of public funds in accordance with the usual procedures generally applicable to all state and local agencies and institutions.

6.5. Site grading and improvement of land, including demolition related to the project.

6.6. Landscaping for public-library-use areas.

6.7. Parking lots, when part of a larger construction project.

6.8. Private building consultant, architectural/engineering/inspection expenses.

6.9. Furnishings and equipment, with a total reimbursable cost of 25% of the total cost of the project.

Not included are:

6.10. Library materials.

6.11. Office supplies.

6.12. Furnishing and equipment in excess of 25 % of the total cost of the project.

6.13. Fundraising costs.

6.14. Non-public-library-use costs for a multipurpose building.

6.15. Salaries of in-house administration or library staff.

6.16. Feasibility studies.

6.17. Lease of facilities, service, equipment, or maintenance contracts.

6.18. Moving expenses.

6.19. Landscaping for non-public-library-use areas.

6.20. Parking lots which are not part of a larger construction project.

Back to Contents


7. Contractor Requirements

7.1. After the agreement has been signed with the Office of Library and Information Services, the library will publicly advertise or circulate the specifications for the project. At least three bids for projects requiring a general contractor or construction manager must be received for the project to proceed.

7.2. After the opening of the bids, the library shall provide the Office of Library and Information Services with a tabulation of bids received.

7.3. The library shall award the contract to the responsible bidder submitting the lowest acceptable bid. A sample letter to the successful bidder is enclosed as Appendix I.

7.4. The actual construction work will be performed by the lump sum (fixed price) contract method. Use of this method does not preclude the use of a construction manager if this is otherwise allowed by the governing body. (Note: RIGL 45-55 covers the award of municipal contracts. See Appendix M.)

7.5. The STATE OF RHODE ISLAND EQUAL OPPORTUNITY COMPLIANCE CERTIFICATE AND AGREEMENT (Appendix J) and the DRUG-FREE WORKPLACE POLICY CONTRACTOR CERTIFICATE OF COMPLIANCE (Appendix L) are required before a contract can be signed by the library. The library will tentatively award the contract, pending a conference to be arranged by the Equal Opportunity Contract Compliance Officer, and the necessary compliance signatures by the contractor.

7.6. A prospective contractor shall include in its bid on any Construction project covered by these regulations, a simple statement acknowledging its obligation to meet the ten percent (10%) requirement for Minority Business Enterprise participation. A Minority Business Enterprises Compliance Plan (Appendix K) shall be submitted to the Director of the Department of Administration or his designee within ten (10) working days of the tentative contract award. The Director or his designee shall review and approve plans that reasonably ensure compliance with the ten percent (10%) requirement. A contractor's failure to have an approved Minority Business Enterprise Compliance Plan constitutes non-compliance.

7.7.  The project contractor/subcontractor shall comply with the Davis Bacon Act as supplemented by the Department of Labor regulations.

7.8. The project contractor/subcontractor shall comply with the Copeland "Anti-Kickback Act".

7.9. After signing the contract, the library will submit a copy of the contract to the Office of Library and Information Services.

Back to Contents


8. Amendments

8.1. Any amendments (change orders) to the project shall be submitted to the Office of Library and Information Services.

Back to Contents


9. Display of Signs

9.1. The site of the construction project shall display a sign stating that state funds administered by the Rhode Island Office of Library and Information Services are being used for such construction.

9.2. If specifications call for a plaque in the completed building indicating the date of completion and sources of funds, state funds administered by the Rhode Island Office of Library and Information Services shall be noted.

Back to Contents


10. Completion of Project

10.1. The library shall complete its construction project within three years of signing a construction agreement with the Office of Library and Information Services, and in accordance with the application and approved drawings and specifications.

10.2. Upon completion of the project, the library shall submit a Certificate of Substantial Completion to the Office of Library and Information Services.

Back to Contents

Adopted by the Library Board of Rhode Island on December 7, 1998; effective February 3, 1999. § 3.10 amended by the Library Board of Rhode Island on October 20, 2003.

Published by the Rhode Island Office of Library and Information Services - August 1998